BMF Enerji Implemented Gas Collection and Cooling System (Booster System) Projects
BMF Enerji successfully commissioned the Gas Collection and Cooling System (Booster System) Projects in Düzce, Ağrı and Manisa in 2020.
In 2021, Istanbul Enerji A.S. Seymen Enerji Production Facility won the 3rd stage Gas Collection and Preconditioning System tender with a capacity of 6,000 m³/h. Within the scope of the project, it will add Blower and Dehumidification (Heat Exchanger) systems with a capacity of 6,000 m³/h to the existing Booster System.
With the additions, the Booster System will have a capacity of 24,000 m³/h. The automation system will be revised and the new automation system with a capacity of 24.000 m³/h will be put into use.
BMF Enerji continues its production and R&D studies in the concept of environmentally friendly industry and production, which is one of the requirements of the 21st century.